Construction experience
Welded pipes
 
-  For full preparation before welding tools, avoiding a waste of time to search.
-  Measured carefully welded length, length after welding installation.
-  Work with insulated gloves, insulated.
-  There should be facilities to maintain steady pressure working voltage.
-  Check the temperature of the laser welding gun.
-  Set up temperature, heat welding and thermal stability at temperatures 240 - 260oC, at least 30 minutes before using.
-  Workers welding needed for sample manipulation mature 2 - 3.
-  Make stages from easy to difficult, adhere to time connecting pipes and fittings.
-  Time stable welding after 2 - 10 minutes, depending on pipe diameter.
-  Check the weld immediately after welding stability.
-  Use NIVO ruler, protractor to ensure the accuracy of welded corners.
-  Welding Equipment is only basic requirements and standards. Depending on site conditions can be worked tube jig rigs, welding racks.
-  After welding, the weld inspection: smoothness of the lumen, external welds have uniform donuts, donuts homogeneous, not grainy, foaming.
 
 
Từ khóa:
Các bài khác
AMY CONSTRUCTION MATERIAL CO., LTD AMY CONSTRUCTION MATERIAL CO., LTD AMY CONSTRUCTION MATERIAL CO., LTD AMY CONSTRUCTION MATERIAL CO., LTD AMY CONSTRUCTION MATERIAL CO., LTD AMY CONSTRUCTION MATERIAL CO., LTD AMY CONSTRUCTION MATERIAL CO., LTD AMY CONSTRUCTION MATERIAL CO., LTD AMY CONSTRUCTION MATERIAL CO., LTD AMY CONSTRUCTION MATERIAL CO., LTD AMY CONSTRUCTION MATERIAL CO., LTD AMY CONSTRUCTION MATERIAL CO., LTD AMY CONSTRUCTION MATERIAL CO., LTD